2025 Schedule
Here are the City streets scheduled to be milled and overlayed in 2025:
- Hundertmark Rd east of Clover Ridge Elementary to Hwy 41
- Brinkhaus St
- Brinkhaus Circle
- Lano St
- Isabella Pkwy
- Holstein Rd
- Bluegrass Rd
- Mulligan Lane
- Georgeanna Dr
- Hilltop Dr
Overlay Basics
- Why these streets? We have evaluated all city streets and have prioritized which streets will be overlayed.
- Is there an assessment? No, this project comes out of the city's normal operating budget. There is no assessment to you or your business.
- When? Work is typically planned for sometime in summer/fall. City crews will install signs at the entrance to the neighborhood letting you know when the project will take place. They will also prune trees with low overhanging branches.
- What happens during a mill and overlay?
- Our contractor will mill 6 to 12 inches of blacktop on the edge of the road. Milling should take 1 to 2 days to complete.
- City crews will follow and raise the manholes and water valves to match them up to the height of the new 2 inches of blacktop.
- Then, the contractor will come back to pave the road. The paving process will take about a week to complete. Paving is weather dependent, so the exact dates might change.
- What's the impact? Please keep all vehicles off the streets during the overlay process. There will be times when traveling to and from your house will take a few extra minutes, so please be patient. We have instructed the contractor to allow for access to homes and businesses on these streets.